Structural openings: trimmers, lintels and the load a lantern adds
How a roof lantern opening is trimmed and where its load actually goes, from glass and kerb down through trimmers, beams and walls, and the point at which calculations are needed.
A lantern is a load standing on a hole you just cut
Every other decision about a roof lantern is reversible on paper. This one is not. The moment a deck is opened, the structure that used to carry that area has to be replaced by something else, and the new thing has to carry more than the old thing did, because a glazed pitched structure weighs considerably more than the square metre of insulation and felt it displaced. A lantern is also a heavier proposition than a flat skylight of the same footprint, which is why a deck that would have accepted one can still need work to accept the other.
That is the whole subject in one sentence, and it is why the order of work on a lantern job is fixed: form and trim the opening, build the kerb on it, measure the kerb, then order. Reversing it, ordering from a drawing and making the roof fit afterwards, is how lanterns end up sitting on packed timber offcuts with a bead of sealant doing structural work.
One boundary before we start. This page is about the roof underneath. How deep the lantern’s own rafters and glazing bars need to be to span its own width, and at what point it needs an intermediate post, is a separate question with its own guide on this site.
Four loads, not one
People picture the weight of the glass and stop there. Building Control does not, and neither does an engineer.
| Load | What it is | Where it goes |
|---|---|---|
| Dead load | The permanent weight of frame, glass, kerb and fixings. Sealed double glazed units are commonly in the order of 25 to 30kg per square metre before the frame is counted, and the manufacturer’s data sheet gives the real figure for the unit you are buying | Down through the kerb into the perimeter of the opening, continuously |
| Imposed load | Snow, and the load allowance for occasional access for maintenance | Onto the lantern, then down the same path as the dead load |
| Wind uplift | Suction. A pitched object on a flat roof is a pressure anomaly, and the worst of it is at the edges and corners | Upward and sideways, which is why the fixings work in tension, not just in shear |
| Point loads | Concentrated load where a ridge lands, where a gable end carries the ridge, or under an intermediate post | Into specific spots that have to be identified and reinforced individually |
What happens when a joist is cut
A flat roof deck is a set of parallel joists spanning between two supports. Cut three of them out to make an opening and you have not simply removed some structure; you have created an unsupported end on six cut joists, and the load those joists were carrying still exists and still has to arrive somewhere.
The answer is a frame within the frame. The two full joists either side of the opening become trimming joists, and they now carry their own share plus the load handed to them from the cut ones. Across the ends of the cut joists run trimmers, short members spanning between the trimming joists and collecting everything. The cut joists themselves become trimmed joists, hanging off those trimmers.
Because the trimming joists are doing roughly double the work, they usually have to be doubled up, bolted together and acting as one member rather than two pieces of timber standing next to each other. That detail, bolted at the right centres rather than nailed, is the one most often skimped, and it is invisible the moment the ceiling goes up.
The connection matters more than the timber
Sizing a trimmer is arithmetic. Connecting it is where jobs go wrong. A trimmer carrying five cut joists has to transfer all of that load into the trimming joists through its end connections, and end grain nailed into the side of another joist transfers very little of anything.
The rule, and the exception
The rule: every trimmed joist hangs off a proper joist hanger, and every trimmer connects to its trimming joists with a hanger too, fully nailed with the correct nails in every hole. Skew nailing is not a connection, it is a way of holding timber still while you fit the hanger.
The exception: a genuinely small opening in a deck with ample joist depth, where nothing needs cutting because the unit fits between two existing joists. That happens more often with a modest flat rooflight than with a lantern, and where it happens the job gets simpler and cheaper, which we will tell you.
What is never an exception: packing. If the kerb does not land squarely on structure, the answer is to move the structure, not to build up the gap with offcuts.

When the opening is in masonry: lintels and padstones
On many extensions the lantern is only half the structural story. The other half is the wall that came out to make the room open plan, and the beam that replaced it. Where a rear extension is knocked through to the original house, there is a steel or a lintel carrying the wall above, and the new flat roof frequently bears on the extension walls at one end and on that opening at the other.
Two things follow. A beam supporting masonry needs proper bearing at each end, which usually means a padstone spreading the load into the wall rather than concentrating it on a few bricks. And the lantern load, once collected by the trimmers, arrives at the wall plate and then at the walls; if part of that route lands over the new opening, it forms part of what the beam has to carry and must be in the calculation from the start.
An old garage wall is the version of this that catches people. Single skin, built for a felt roof and a garage door, and now proposed as the bearing for a kitchen extension roof with a lantern on it. That wall was never designed for the job and it usually cannot be talked into it.
Point loads: the ones that do not spread
A hipped lantern spreads its load fairly evenly round the whole perimeter ring, which is convenient because it means the kerb and the trimmed opening below it share the work. A gable ended lantern does not. The ridge becomes a beam carried at two points, and those two points push down hard on a short length of kerb at each end.
An intermediate post in a wide unit is the same problem in the middle of the roof. So is a corner post on a large square lantern. Each of them is a concentrated load that has to be traced down through the kerb, through the deck, into a joist or a beam, and onward to a wall or a pad. Spreading it with a timber plate under the kerb helps, but it does not remove the need to know where it lands.
This is the practical reason the end style and the structural design have to be settled together rather than in sequence. Choosing a gable end after the opening has been trimmed for a hip is a change to the structure, not a change to the glazing order.
Tracing the load all the way down
- The glass and frame sit on the kerb. Fixed at the centres the manufacturer specifies, into the kerb top plate, at the fixing grade the exposure zone calls for.
- The kerb sits on the trimmed opening. Directly over structure round its whole perimeter, not over a deck board bridging a gap.
- The trimmers collect the cut joists. Hung, not nailed, and sized for what they are actually carrying rather than matched to the joists beside them.
- The trimming joists take it to the ends. Doubled where the calculation says so, and acting as a single member.
- The wall plates take it to the walls. Or, where the deck bears on a beam over a knocked through opening, into that beam.
- The walls take it to the foundations. Which is where the question becomes whether the existing wall and footing were ever built for this.
Six links. A lantern job fails at whichever of them was assumed rather than checked, and it is almost never the first one.

When a structural engineer is needed
Where we stop and someone else starts
We are glazing installers, not structural engineers, and we do not issue calculations. What we do is identify, at survey, when calculations are needed and say so in writing before anything is ordered.
Assume an engineer is involved where: the opening removes more than a couple of joists; the lantern is large or gable ended with real point loads; the deck bears on a beam over a knocked through wall; the existing structure is a trussed or lightweight deck; or the roof is being altered at the same time as anything else structural.
You may not need one where: a small unit drops into an opening between existing joists with nothing cut, in a deck of generous depth, and Building Control is content with a standard detail. That is a real outcome and not a rare one, but it is confirmed, not assumed.
The Poole roofs where this bites hardest
Post-war estate roofs around Canford Heath, Creekmoor and Alderney are the usual surprise. Many flat roofed extensions and garages on that stock were framed as economically as the covering allowed, with shallow joists carrying a felt deck and nothing else. They are perfectly sound for what they were built to do. Asking one to carry a pitched glazed structure is a different question and it needs opening up and checking rather than assuming.
The exposure point cuts the other way here. Inland Poole is sheltered, so the wind uplift case is mild and the fixing specification is ordinary. Out on the Sandbanks spit the dead load argument is identical but the uplift case is severe, because there is no fetch break at all, and the fixings and their pull out values become the governing detail rather than an afterthought.
Building Control, and the order things happen in
Structural alteration to a roof is notifiable work. Which authority receives it depends on the address: BCP Council for Poole, Bournemouth and Christchurch, Dorset Council for Wareham, Swanage, Corfe Castle and Wimborne, New Forest District Council for Lymington and Ringwood. An approved inspector can be used instead in any of them. The technical requirement is national; the process and the people are not.
The sequence that keeps everyone comfortable is simple and it is the same everywhere. Survey and open up enough to see what is there. Get calculations where they are needed. Submit. Form and trim the opening. Have it inspected while it is still visible, because once the kerb and the ceiling are on, nobody can see a single one of these connections again. Then build the kerb, measure it, order, and glaze.
What we put in writing
The survey says what we found in the deck, what we think has to change, and whether calculations are needed. You get a fixed written price against that. If something genuinely unforeseeable turns up once the deck is open, soft timber under an intact covering being the usual one, we stop, show you, and price the repair separately before going on.
Our installation work carries a ten year workmanship guarantee. It is a workmanship guarantee and it is not insurance backed. If you want to know whether your deck is likely to need trimming before you commit to a lantern rather than a flat rooflight, ring 01202 923272 and describe the roof.
Related reading
Can a roof lantern be fitted in winter?
Yes. Winter changes how the working day is organised, not whether a roof lantern can be installed. Cold is a…
Can a roof lantern be made to open?
Yes, but it is decided at order, not afterwards A roof lantern can be made to open. Most systems offer…
Can a roof lantern go on a pitched roof?
Not onto the slope itself. A roof lantern is designed to stand on a level kerb, and a pitched roof…
Can a roof lantern go over a garage conversion?
Frequently yes — but the garage decides, not the lantern Garage conversions are one of the better places to put…
Can a roof lantern sit on a flat roof without a kerb?
No. A roof lantern has to stand on an upstand of some kind — either a kerb built on site…
Can one cracked pane in a roof lantern be replaced on its own?
Normally yes, and that is a designed-in advantage of the format A roof lantern is assembled from a frame, a…