How long does fitting a roof lantern take?

The short answer

A straight replacement into a sound existing kerb is a day. A new opening is typically two to three days on site. In both cases the roof is only genuinely open for a few hours, not for the whole job — which is the part people are actually asking about.

Section through a roof lantern on a kerbA roof lantern is a pitched glazed structure standing on a kerb above a flat roof. The pitch sheds water and debris and distributes light; it is not a flat rooflight with a hat on.ridge barglazing barkerbflat roof deckpitch sheds water

Three jobs, three answers

“Fitting a roof lantern” covers work of very different sizes, and quoting one duration for all of it is how firms end up on site for a week having promised a day.

A like-for-like replacement into a kerb that is square, sound and the right size is a single day: old unit out, kerb checked and made good, new frame set, glazed, capped, tested. That is true whether the thing coming off is a lantern or a flat rooflight. A new opening in an existing flat roof is two to three days, because the deck has to be cut, the joists trimmed, the kerb built, the covering dressed and terminated, and only then does any glazing happen. A lantern as part of an extension has no separate duration at all — it is a day or two inside someone else’s programme, and the sequencing matters more than the count.

How long the roof is actually open

The number people mean when they ask

On a new opening, the deck is cut and the opening is trimmed and made weathertight within the same working day. The house is never left with a hole in the roof overnight. If the glazing cannot go in that day, the opening is decked over and covered, not tarped over and hoped about.

On a replacement, the gap between the old unit coming off and the new frame going on is measured in a couple of hours with a cover standing by.

A new opening, day by day

  1. Day one, morning. Protection down inside, access up outside, the route agreed. The opening marked from below and checked against the joists above.
  2. Day one, afternoon. Deck cut, joists trimmed and hung, opening squared, kerb framed and insulated. Weathertight before anyone leaves.
  3. Day two, morning. Roof covering dressed up the kerb and terminated. This is the part that decides whether the lantern leaks in five years, and it is not rushed to make room for the glazing.
  4. Day two, afternoon. Frame bedded, levelled, fixed at the correct centres. Panes lifted in one at a time, gaskets and caps fitted, ridge closed.
  5. Day three where needed. Hose test, internal reveal made good if it is in scope, plaster or plasterboard finished, site cleared, paperwork handed over.

Some jobs finish inside two days. We would rather schedule three and give you the day back than book two and be there on Saturday.

What stretches it

What we find Effect on the schedule Why
Soft deck under an intact covering Half a day to two days The commonest genuine surprise. Rotten boarding cannot be built on and has to come out first
An old opening formed without trimmers A day, sometimes a return visit The structure has to be put right before the new unit goes anywhere near it
Restricted access Half a day, sometimes a mechanical lift Panes that cannot be carried through have to be lifted over, which changes the whole method. A large skylight pane and a narrow side passage are a common combination
A Building Control inspection stage Whatever the appointment costs The trimmed opening is inspected before it is covered, so the programme waits on a visit, not on us
Internal finishing in scope A day, plus drying time Plaster does not dry to order. If the reveal is being finished wet, that is a separate visit

Lead time is not fit time

The days on site are the small half of the calendar. Between survey and installation sits the manufacturing lead time for the lantern itself, which for a made-to-measure unit is weeks rather than days, and longer for non-standard colours, non-standard glass or anything with an opening vent in it.

That lead time is not wasted. The opening is not cut until the unit is made and checked, because cutting a roof to a size that later turns out to be wrong is the most expensive mistake available on this kind of job. It also means a date offered before the unit is confirmed is a hope rather than a booking, and we do not offer those.

Weather, and the Poole version of it

The stopper is wind, not rain, and Poole gives you different amounts of it within four miles. At Sandbanks and the harbour mouth the south-westerly arrives with nothing to break it, so lift days are chosen against the forecast far more carefully than they are for the same job in Broadstone or Creekmoor. Glass does not go up a scaffold in a gust for anybody.

Behind the Old Town the land takes the edge off. In Canford Cliffs and Branksome Park the mature pine canopy shelters the roof but complicates the crane position, which is a different constraint with the same effect on the diary.

A wind hold moves a lift; it does not usually move the whole job, because the cutting, trimming and kerb work all carry on. More on cold-weather working is on whether a roof lantern can be fitted in winter.

What we commit to on dates

A start date confirmed once the unit is confirmed. A stated number of days on site, with the reason if it changes. The roof weathertight at the end of every day without exception. And a fixed written price agreed after survey, so a schedule that runs long is our problem rather than a line on an invoice.

Our installation work carries a ten-year workmanship guarantee. It is a workmanship guarantee and it is not insurance backed, and we say so rather than let the phrase do work it has not earned. To get dates for your own roof, ring 01202 923272 or book a survey.

Get a fixed quote

Get a fixed quote

Tell us which way your roof faces.

We will come back with a specification, not a catalogue page. If your extension faces south we will tell you the G-value we would fit and why.

  • No pressure, no doorstep sales call
  • We handle the Building Control notification
  • 10-year workmanship guarantee on every installation
  • Installations and replacements across Poole and south Dorset

Prefer to talk it through? 01202 923272