Can a rooflight be replaced in one day?

The short answer

The fitting usually is, yes. One rooflight, on a roof that can be reached, onto a kerb that turns out to be sound, is a single day from protecting the room to testing the finished perimeter. What is not a day is everything around it: the unit is made to order after the survey, access may need erecting first, and anything found in the upstand once the old skylight is off has to be dealt with before the new one goes down.

How a sealed unit fails and mistsA sealed unit holds dry air or argon between two panes, kept dry by desiccant in the spacer bar. Daily heating and cooling pumps the cavity; once the edge seal loses its grip, moist air is drawn in, the desiccant saturates, and the misting that appears between the panes cannot be cleaned because it is on the inside.cavity: dry air or argonspacer with desiccantedge sealmisting sits between the panes, so it cannot be cleaned offmoist air

What “a day” actually covers

It covers protecting the room below, removing the old unit, clearing and preparing the kerb, bedding and fixing the replacement, terminating the covering at the upstand, water testing it and clearing away. On an ordinary single-storey extension with a tower already up, that is a comfortable day with time in hand for something to be slightly worse than expected.

The part that is not a day

  1. The survey, which is where the kerb is measured and the specification settled. Nothing is ordered before it.
  2. Manufacture. Flat rooflights and lanterns are made to the measured size, so the glass is made after the survey rather than taken off a shelf.
  3. Any permission that applies: a building control notice, or a highway licence where access goes on a public footway.
  4. Erecting access, which on a two-storey roof is frequently a separate visit before the fitting day and another one afterwards to take it down.
  5. The fitting itself, which is the day everybody means.
  6. Decoration, if a reveal has had to be made good, because plaster has to dry before it takes paint.

Five things that push it past one day

What is found Why it adds time Can it be known in advance?
Soft timber in the upstand The kerb is rebuilt rather than reused, which is carpentry and then roofing Mostly. Sounding the upstand at survey finds most of it
A wet deck under the perimeter The deck has to dry or be replaced before anything is bedded on it Only by opening a small area, which we would rather do at survey
The covering needs cutting back Termination becomes a roofing operation with its own materials and curing Usually, from how the old unit was detailed
Access on the public highway Erect, work, dismantle: three visits rather than one Entirely. It is decided before a date is offered
Weather turning The opening is closed and made weathertight, and the work resumes another day Partly, and it is why we hold a fallback date on exposed roofs

Access is often the second day nobody counted

On a single-storey rear extension a tower goes up and comes down within the fitting day. On a two-storey roof, or anywhere a scaffold is needed, the structure arrives before and leaves after, and those are separate visits by a separate trade with their own scheduling. The glazing is still one day. The job is three appointments.

That is worth knowing because it changes what you are agreeing to when somebody tells you a replacement is a one-day job. Ask which day they mean.

The rule that does not bend for the diary

An open roof is never left to chance

We do not open a roof until the replacement is on site and the weather window is confirmed. A unit that has not arrived, a forecast that has turned, or a wind picking up off the water are all reasons to move a day, and moving it costs everyone far less than an opening covered with a sheet overnight.

And if the work cannot be finished, the opening is closed properly before anyone leaves. Not weighted down, not taped: mechanically fixed and weathertight, every time. If that means a second day, we say so on the day rather than rushing a bedding detail to be off site by five.

Two or three units on the same roof

Often yes, and it is usually the better way to do it. Where several units are the same size and the access serves them all, the second and third are considerably quicker than the first, because the protection, the access and the setting out are already done. Where they are different sizes or on different roof areas, it is a two-day job and we will say so at quotation rather than start optimistically.

Making good, and what is not included

A straight like-for-like swap normally leaves the inside untouched. Where the reveal has been stained by a leak or disturbed during removal, it is cut back and made good on the day, but the plaster then needs to dry before anyone paints it. Decoration is a later job and it is stated on the quotation as included or not included, because that is the commonest misunderstanding in this trade and it is easily avoided in writing.

What sets a date in this part of Dorset

Two local things move dates more than anything else here. The first is access licensing: in Poole, Bournemouth and Christchurch that is BCP Council, in Wareham, Swanage and Wimborne it is Dorset Council, and across the county line at Lymington and Ringwood it is a Hampshire authority with New Forest District Council on the planning side. Each has its own lead time, and a start date given before a licence exists is a guess. The second is wind off the water. A large unit is a sail, and on the sand spit at Sandbanks, at the harbour mouth and along the Quay there is a wind speed above which a lift does not happen that day. Four miles inland at Broadstone or Creekmoor that constraint barely registers, which is why the same job carries a different amount of programme risk depending on the postcode.

What we commit to in writing

After the survey you get a fixed written price, the specification of what is going in, the Building Regulations position, and an honest programme: the lead time for manufacture, whether access needs a separate visit, and how many days on site the work is expected to take. We do not quote a duration from a phone call any more than we quote a price from one. Our installation work carries a ten-year workmanship guarantee, given directly by us, which is not insurance backed. To get a date looked at, ring 01202 923272 or send photographs of the rooflight and the roof around it to 447880284133.

Get a fixed quote

Get a fixed quote

Tell us which way your roof faces.

We will come back with a specification, not a catalogue page. If your extension faces south we will tell you the G-value we would fit and why.

  • No pressure, no doorstep sales call
  • We handle the Building Control notification
  • 10-year workmanship guarantee on every installation
  • Installations and replacements across Poole and south Dorset

Prefer to talk it through? 01202 923272