Can a rooflight be replaced in one day?
The fitting usually is, yes. One rooflight, on a roof that can be reached, onto a kerb that turns out to be sound, is a single day from protecting the room to testing the finished perimeter. What is not a day is everything around it: the unit is made to order after the survey, access may need erecting first, and anything found in the upstand once the old skylight is off has to be dealt with before the new one goes down.
What “a day” actually covers
It covers protecting the room below, removing the old unit, clearing and preparing the kerb, bedding and fixing the replacement, terminating the covering at the upstand, water testing it and clearing away. On an ordinary single-storey extension with a tower already up, that is a comfortable day with time in hand for something to be slightly worse than expected.
The part that is not a day
- The survey, which is where the kerb is measured and the specification settled. Nothing is ordered before it.
- Manufacture. Flat rooflights and lanterns are made to the measured size, so the glass is made after the survey rather than taken off a shelf.
- Any permission that applies: a building control notice, or a highway licence where access goes on a public footway.
- Erecting access, which on a two-storey roof is frequently a separate visit before the fitting day and another one afterwards to take it down.
- The fitting itself, which is the day everybody means.
- Decoration, if a reveal has had to be made good, because plaster has to dry before it takes paint.
Five things that push it past one day
| What is found | Why it adds time | Can it be known in advance? |
|---|---|---|
| Soft timber in the upstand | The kerb is rebuilt rather than reused, which is carpentry and then roofing | Mostly. Sounding the upstand at survey finds most of it |
| A wet deck under the perimeter | The deck has to dry or be replaced before anything is bedded on it | Only by opening a small area, which we would rather do at survey |
| The covering needs cutting back | Termination becomes a roofing operation with its own materials and curing | Usually, from how the old unit was detailed |
| Access on the public highway | Erect, work, dismantle: three visits rather than one | Entirely. It is decided before a date is offered |
| Weather turning | The opening is closed and made weathertight, and the work resumes another day | Partly, and it is why we hold a fallback date on exposed roofs |
Access is often the second day nobody counted
On a single-storey rear extension a tower goes up and comes down within the fitting day. On a two-storey roof, or anywhere a scaffold is needed, the structure arrives before and leaves after, and those are separate visits by a separate trade with their own scheduling. The glazing is still one day. The job is three appointments.
That is worth knowing because it changes what you are agreeing to when somebody tells you a replacement is a one-day job. Ask which day they mean.
The rule that does not bend for the diary
An open roof is never left to chance
We do not open a roof until the replacement is on site and the weather window is confirmed. A unit that has not arrived, a forecast that has turned, or a wind picking up off the water are all reasons to move a day, and moving it costs everyone far less than an opening covered with a sheet overnight.
And if the work cannot be finished, the opening is closed properly before anyone leaves. Not weighted down, not taped: mechanically fixed and weathertight, every time. If that means a second day, we say so on the day rather than rushing a bedding detail to be off site by five.
Two or three units on the same roof
Often yes, and it is usually the better way to do it. Where several units are the same size and the access serves them all, the second and third are considerably quicker than the first, because the protection, the access and the setting out are already done. Where they are different sizes or on different roof areas, it is a two-day job and we will say so at quotation rather than start optimistically.
Making good, and what is not included
A straight like-for-like swap normally leaves the inside untouched. Where the reveal has been stained by a leak or disturbed during removal, it is cut back and made good on the day, but the plaster then needs to dry before anyone paints it. Decoration is a later job and it is stated on the quotation as included or not included, because that is the commonest misunderstanding in this trade and it is easily avoided in writing.
What sets a date in this part of Dorset
Two local things move dates more than anything else here. The first is access licensing: in Poole, Bournemouth and Christchurch that is BCP Council, in Wareham, Swanage and Wimborne it is Dorset Council, and across the county line at Lymington and Ringwood it is a Hampshire authority with New Forest District Council on the planning side. Each has its own lead time, and a start date given before a licence exists is a guess. The second is wind off the water. A large unit is a sail, and on the sand spit at Sandbanks, at the harbour mouth and along the Quay there is a wind speed above which a lift does not happen that day. Four miles inland at Broadstone or Creekmoor that constraint barely registers, which is why the same job carries a different amount of programme risk depending on the postcode.
What we commit to in writing
After the survey you get a fixed written price, the specification of what is going in, the Building Regulations position, and an honest programme: the lead time for manufacture, whether access needs a separate visit, and how many days on site the work is expected to take. We do not quote a duration from a phone call any more than we quote a price from one. Our installation work carries a ten-year workmanship guarantee, given directly by us, which is not insurance backed. To get a date looked at, ring 01202 923272 or send photographs of the rooflight and the roof around it to 447880284133.
Related reading
Are 1990s rooflights on Poole extensions worth replacing now?
In most cases yes, and usually not for the reason people expect. A 1990s unit that has misted is finished…
Can a leaking rooflight be resealed instead of replaced?
Sometimes, where the leak is at a gasket, a termination or a joint that can genuinely be renewed. But the…
Can a misted rooflight be repaired?
Sometimes, but not in the way most people mean. The misting itself cannot be cured, because the fault is inside…
Can a misted unit be replaced with a larger one?
Yes, and it is often worth doing while the roof is open. But be clear what you are agreeing to:…
Can an old dome rooflight be swapped for flat glass?
Yes, and it is one of the replacements people are most pleased with afterwards. The work is usually straightforward, because…
Changing the glass without changing the frame, and when that works
Whether you can change the glass and keep the frame comes down to one thing: how the frame holds the…