Setting out a rooflight so the plasterboard reveal lines up
Three trades set a rooflight out against three different datums. Which one wins, where the error has to be absorbed, and the two moments that cannot be undone.
One rooflight, set out three times, by three different trades
A flat roof rooflight gets positioned at least three times before anyone sees it. The carpenter sets out the opening against the joists. The roofer sets out the kerb against the fall and the covering. The plasterer sets out the reveal against the ceiling, the walls and the eye. Each of them is working to a different reference, on a different day, and frequently without having seen the other two do it.
When those three agree, you get a skylight that looks as though the room was built around it. When they disagree by fifteen or twenty millimetres, you get a reveal that is wider at one end than the other, or a light shaft that is visibly off-centre against the ceiling, and no amount of good glass rescues it.
The fix is not craftsmanship applied later. It is setting out from the right datum at the start, and knowing which of the three references wins when they conflict.
What “out” actually looks like from the sofa
The human eye is extraordinarily good at parallel lines and extraordinarily bad at absolute position. A rooflight sitting 40mm off the true centre of a ceiling is almost impossible to notice, because there is nothing to compare it against. A reveal that is 95mm deep at one end and 110mm at the other is noticed immediately by everyone who walks in, because the two edges of the shaft are right next to each other and the taper between them is obvious. This is the single most useful thing to know about setting out a rooflight: consistency beats accuracy. Get the shaft parallel and even, and nobody will ever measure where it sits.
Set out from the inside, build from the outside
The instinct on site is to work from the roof, because that is where the job starts and where the structure is visible. It produces reveals that are out, because the roof’s references — joist positions, the fall, the existing covering laps — have nothing to do with the references the finished room will be judged against.
So the discipline is the other way round. Decide where the shaft should read from inside the room first: which wall it should sit parallel to, what it should be centred on, where the light should land. Mark that on the ceiling. Then transfer those marks up through the structure and let the roofing work follow them, adjusting only where the structure genuinely will not allow it — and when that happens, adjust in the direction that keeps the shaft parallel rather than the direction that keeps it central.
Who owns which millimetre
| Stage | Realistic tolerance | What absorbs an error here | What happens if it is not absorbed |
|---|---|---|---|
| Structural opening | Coarse — a few millimetres either way is normal | The kerb, which is built to the opening rather than to the drawing | Nothing visible, provided the next stage is measured off what was built |
| Kerb | Tight — square, plumb and flat within a very few millimetres | Almost nothing; the glazed unit is rigid and will not take it up | Uneven gasket compression above, and an out-of-square shaft below |
| Unit on the kerb | Fixed by the manufacturer | Nothing — it is made to a size before it arrives | A unit that does not sit down evenly on its seating |
| Plasterboard reveal | Fine — this is the surface being looked at | Battens and packers behind the board, which is where accumulated error is meant to be taken out | A tapered shaft, visible from the whole room, permanently |
| Ceiling line | Whatever the existing house gives you | A shadow gap or a deliberate reveal detail at the junction | A crack along the junction within the first heating season |
Read down that table and the pattern is clear: the error has to be taken out at the reveal battens, and the reveal battens can only take it out if someone left room for them. That is the whole argument for setting out early rather than hoping later.

Diagonals, not edges
An opening can have four edges of exactly the right length and still be a parallelogram. Measuring the sides tells you nothing about square; measuring the two diagonals tells you everything, and the check takes under a minute at a stage where correction is free.
The same applies to the kerb once it is up, and to the batten frame before the boards go on. Three diagonal checks across a job, at three different stages, is the difference between a shaft that reads clean and one that is subtly wrong in a way nobody can name. Out of square is worse than out of position for exactly the reason set out above: it shows as a taper, and a taper is a comparison the eye makes without being asked.
The setting-out sequence, in order
- Agree the position from inside the room. Standing where people will stand. Marked on the existing ceiling, with the line you are centring on written down — the room’s centre, a wall, a run of units, a table.
- Establish the joists and their direction, and reconcile the desired position with what the structure allows. Where they fight, move the opening a whole bay rather than a few centimetres, and keep the shaft parallel to the room.
- Transfer the marks upward through the ceiling at the corners, so the roof-level setting out is the room’s setting out rather than a fresh attempt at it.
- Form and trim the opening, then measure what was actually built. Not what was drawn.
- Build the kerb to that measurement, check diagonals, plumb and twist before any covering, and record the finished internal dimensions.
- Order or fit the unit off the finished kerb, which on a new opening is why there is a pause between the first visit and the second.
- Batten the reveal off a line, not off the kerb face. Snap a line for each face of the shaft, pack out to it, and let the packers absorb whatever the kerb gave you.
- Board, tape and finish, with the ceiling junction detailed deliberately rather than simply filled.
Joists rarely land where the room wants them
The most common conflict on a Poole extension or a converted flat-roofed addition is that the perfect position for the light puts one edge of the opening directly on a joist. There are three ways out, and they are not equal.
You can move the opening to the next bay, which keeps the structural work trivial and moves the shaft — usually acceptable, because absolute position is the thing nobody notices. You can cut the joist and trim the opening, which is routine work and costs what it costs. Or you can size the unit to fit cleanly between joists, which is free and often produces a narrower rooflight than the room deserves. Which of the three is right depends on the structure, and our guide to post-war estate flat roofs and the spans they allow goes into what each one involves.
The reveal sits inside the kerb, not on it
The rule, and where it is deliberately broken
The rule: the finished reveal should be battened off independent lines inside the kerb opening, with packers taking up the difference. Boarding directly onto the inside face of the kerb transfers every millimetre of the kerb’s error straight into the surface you look at, and gives the insulation nowhere to run past the frame.
Broken deliberately, case one — a splayed reveal. Where the shaft is splayed to throw light further into the room, the battens set the angle and the kerb becomes irrelevant to the finished geometry. What each reveal shape does to the light is a subject in its own right and we cover it on our reveal design page.
Broken deliberately, case two — minimum headroom. In a low garage conversion every millimetre of shaft depth is being fought for, and a thinner build-up may be chosen knowingly. Knowingly is the operative word: it should be a decision with a reason, not a discovery on the day the plasterer arrives.

The errors we get called to look at
| What it looks like | Where it came from | Can it still be fixed? |
|---|---|---|
| Shaft wider at one end than the other | Reveal boarded off an out-of-square kerb | Yes — reveal only, if the kerb itself is sound |
| Rooflight visibly not parallel to the walls | Opening set out from the roof rather than the room | Only by moving the opening, which means roof work |
| Crack along the ceiling junction in year one | Board butted hard to the ceiling with no movement detail | Yes — cut in a shadow gap and stop filling it every spring |
| Dark corners inside the shaft | Insulation voids behind the board at the corners | Yes, but the reveal has to come off to do it properly |
| Frame edge visible inside the room | Reveal set too wide, exposing the unit’s frame instead of stopping at it | Usually, by re-battening one or two faces |
| No room for the blind that was always planned | Nobody told the plasterer there would be one | Sometimes, and it is much cheaper to have mentioned it |
Two moments that cannot be undone
The first is the moment the opening is formed. After that, the position of the rooflight in the room is fixed, and every later stage is working with the consequences. It is worth five minutes of standing in the room with a tape and arguing about it, and we would far rather have that conversation than proceed politely to the wrong place.
The second is the moment the covering is dressed up the kerb. Until then the kerb can be adjusted, packed, or rebuilt in an afternoon. Afterwards it is welded, bonded or laminated into a waterproof system, and changing it means undoing weatherproofing that was working. Everything about the kerb — height, square, twist, and the internal dimensions the reveal will eventually be set out from — gets checked and written down before that happens, because that is the last cheap moment in the job.
What we do about it on our own jobs
Stated plainly
The position is agreed inside the room before anything is cut, with you standing there, and marked on the ceiling rather than described.
The finished kerb dimensions are recorded and handed on to whoever is forming the reveal, including where we are not doing that part ourselves. Most reveal problems are handover problems.
A fixed written price after survey that says whether the reveal is in our scope or somebody else’s, because “rooflight fitted” is the phrase under which this work most often goes missing between two trades.
A ten-year workmanship guarantee on our installation — a workmanship guarantee, and not insurance backed.
If you are planning a flat rooflight into an extension anywhere between Wimborne and Swanage and want the shaft to read properly from the room rather than merely be watertight, ring 01202 923272 before the ceiling is set out. That is the cheap moment.
Related reading
Broadstone and Creekmoor roofs where standard specification is right
Standard specification is the right answer here, and we will say so Most of this site argues that a flat…
Can a flat rooflight be fitted from inside?
Effectively no — not the part that keeps water out. A flat roof rooflight is weathered by dressing the roof…
Can a flat rooflight be fitted to a shed or outbuilding roof?
Yes, and it is usually the simplest work we do Yes. A flat rooflight goes into a garage, workshop, garden…
Can a flat rooflight be retro-fitted to an existing flat roof?
Yes — retro-fitting into an existing flat roof is the majority of this work, not the exception. What decides whether…
Can I fit a flat rooflight to a felt roof?
Yes, and felt is one of the more forgiving coverings to detail Yes. A flat rooflight can be fitted to…
Can two flat rooflights be fitted side by side?
Yes, and it is a common arrangement — but the interesting part is not the two units, it is the…