Point load, distributed load and the numbers a walk-on unit must meet
How imposed load works on a walk-on rooflight, why the concentrated case usually governs on glass, who names the use category, and the design brief a glass maker needs before quoting.
There is no single number that describes what a walk-on rooflight will hold. There are two numbers, owned by two different people, and a walk-on project goes wrong at the exact moment each of them assumes the other has dealt with both.
Ask a glazing supplier what load a walk-on unit takes and you will get a straight answer about the glass. Ask a structural engineer the same question and you will get a straight answer about the opening. Both answers are correct. Neither is the whole thing, and putting them together is not a formality — it is the design.
The two jobs, and the gap between them
| Design job | Who owns it | What they need to be given |
|---|---|---|
| The structure around the opening | A structural engineer, usually the one already on your project | The building, the intended use of the terrace, and the weight of the finished unit |
| The glass itself | The glass maker’s technical department | The measured clear span, the support condition on each edge, and the load category the engineer has named |
| The frame and bearing | The rooflight manufacturer, working to both of the above | Deflection limits from the engineer, glass weight from the maker |
| Getting it right on site | Us | Both documents, before anything is ordered |
The engineer names the use category. The maker designs the glass to it. We build to both and we put no load figure of our own on anybody’s drawing, because a wrong number here is a safety claim rather than a typo.
Distributed load: the number that describes a crowd
A distributed load is weight spread evenly across the surface, expressed as a force per square metre. It is the number that answers questions like “what if the whole family is out there” or “what if it snows on it”. Conceptually it is the easy one: take the area, multiply, and you have a total.
Distributed load is what most people are imagining when they ask how much a walk-on skylight will hold, and it is usually the number that feels reassuring, because the arithmetic gives a total far larger than the number of people who will realistically be standing on a domestic terrace at once. It is also, on glass, very often not the number that governs.
Point load: the number that describes a heel
A concentrated load — a point load — is the same idea with the weight pushed through a small square instead of spread out. It describes a stiletto, a chair leg, a ladder foot, the corner of a paving slab set down for a moment, the spike of a parasol base.
Glass responds to concentration in a way that a timber floor does not. A joisted floor spreads a point load sideways through the boards and into several joists; a pane of glass takes it in bending locally, with the highest stress directly under the point and a second stress peak on the underside of the pane. On a walk-on build-up the concentrated case regularly governs the design even when the distributed figure looks comfortable, which is why a specification cannot be sanity checked by working out what four adults weigh.
Why the “how many people” question misses
People are not the load case. Four adults standing still, spread out, is gentle. One adult stepping down off a step onto a small hard heel is not, and neither is a plant pot set down hard on one corner of its rim.
It is also why we never answer with a weight. A figure in kilogrammes invites someone to do arithmetic that the glass does not follow, and to conclude the pane is fine for something it was never designed against.
Use categories, and who names yours
Imposed loads for floors in the UK come from BS EN 1991-1-1 with its UK National Annex. The standard does not publish a figure for “a walk-on rooflight”. It sorts floor areas into use categories — domestic rooms, balconies, areas subject to wider public access, areas where people might congregate — and each category carries both a distributed value and a separate concentrated value.
Which category applies to your glass is a judgement about the building, not about the product. The same pane in the same house can fall into different categories depending on what it is part of: a private terrace off a bedroom, a balcony, or the path every visitor takes from the gate to the front door. That judgement belongs to the engineer, in writing, and everything downstream follows from it.
Tell the engineer what the terrace is actually for, not what the drawing calls it. The difference between a private sun terrace and a route used by every delivery, trade and guest is a different category, a different glass build-up and a different price. Deciding it honestly at design stage costs a conversation; discovering it afterwards costs a pane.

Deflection: the number you feel before you see
Strength is not the only limit. Long before a pane is anywhere near breaking, it bends, and glass that bends visibly under a footfall is deeply unpleasant to walk on even when it is entirely safe. Structural glass design therefore carries a serviceability limit — a maximum deflection at the centre of the pane, set as a proportion of the span, and it is frequently this limit rather than strength that fixes how thick the glass ends up.
Two practical consequences. First, a pane that feels reassuringly solid is usually one designed with deflection in mind, not simply a thick one. Second, the frame has to be at least as stiff as the glass expects: a beautifully engineered pane set on a supporting steel that itself sags under load will still move, and glass does not tolerate its supports moving differently at different points around the perimeter.
Load duration, and glass asked to hold still for years
A person crossing a terrace is a load for two seconds. A planter full of wet compost is a load for a decade. Glass and interlayers treat those two things very differently, and the difference is the reason a walk-on specification asks what will be left standing on the pane permanently.
- Short duration. Footfall, a gust, someone jumping. The interlayer is stiff at this timescale and the stack behaves close to a single plate.
- Medium duration. Furniture out for a season, a barbecue, a gathering. Still fine, but it needs to have been declared.
- Long duration. Permanent planters, a fixed bench, a water feature, a stack of paving. Sustained load lets a soft interlayer creep, and it is the case that quietly falls outside the design.
- Combined with heat. A south-facing harbour terrace in July is the worst combination: sustained weight on a warm interlayer. This is where interlayer grade earns its money.
- The rule of thumb. If it is not going to be lifted off, it is part of the design brief and it belongs on the enquiry rather than in the garden centre trolley.
The design brief a glass maker actually needs
Most of the delay on a walk-on rooflight order is not manufacturing. It is the technical department asking for information that could have been sent on day one. The list is short and it is always the same.
| What they ask for | Why it changes the glass | Where the answer comes from |
|---|---|---|
| Clear span, both directions | Thickness scales hard with span; a small increase is not a small change | Measured on site, not taken from a plan |
| Support condition per edge | Bearing on four edges is a different pane from bearing on two | The frame design and the engineer’s detail |
| Load category | Sets both the distributed and the concentrated case | The engineer, named in writing |
| Permanent items on the pane | Adds a sustained load case the standard categories do not cover | You, at survey |
| Whether there is a room below | Drives residual capacity, laminated inner pane and thermal performance | The building |
| Surface finish required | Frit and texture are applied to a specific surface during manufacture | Decided at survey, standing in the room below |

Where the load goes once it leaves the glass
The pane hands everything it carries to its perimeter, and the perimeter hands it to a building that was never built to be a floor at that point. This is the engineer’s half and it is the half most often underestimated, because it is invisible in a brochure photograph.
A flat roof deck is designed for its own weight, a covering, insulation, wind and maintenance access. Cutting an opening in it removes structure and then asks what is left to take a concentrated line load all the way round a hole — plus the two hundred kilogrammes or so of glass sitting in it permanently. The answer usually involves trimmers or a steel frame, new bearings, and a check on what those bearings are standing on. The steel framing guide takes that detail on properly.
Test panes, mock-ups and when they earn their place
Structural glass is normally designed by calculation, and for a domestic walk-on rooflight over an ordinary span that is the whole of it. Physical testing enters the conversation on the unusual jobs: a span beyond the maker’s standard range, an odd shape, a pane supported on two edges only where it would rather have four, or a use category that sits above the domestic ones.
Where a maker offers a test report against a specific build-up, that is worth more than a general assurance, because it is evidence about the actual sandwich rather than a family of them. Where a bespoke test is proposed, it is a cost and a delay, and it is proposed for a reason — usually that the design is at the edge of what calculation alone will support.
What we will and will not do with a number
We will read the engineer’s category off the drawing, send it to the maker with the measured span and the support condition, and put the returned build-up on the order unaltered. We will check the frame is specified to the deflection the engineer allows, and we will make the bearing continuous rather than improvised.
What we will not do
We will not invent a load figure, convert one into an equivalent number of people, or tell you a pane is fine for something nobody designed it against.
Where no engineer is appointed, the specification waits. We say so at survey rather than ordering glass against an assumption — and where a non-trafficked skylight with a guard around it would do the same job for a fraction of the cost, that is what the survey will say instead.
Our work carries a ten-year workmanship guarantee, stated plainly as not insurance backed, and a fixed written price after we have measured the opening. Ring 01202 923272 or request a survey. The companion piece to this one is the build-up guide, which explains what the maker does with the category once they have it.
Related reading
Anti slip surfaces and the frit pattern that stays grippy when wet
Slip resistance on a walk-on rooflight is not an opinion about texture. It is a measured number, taken with a…
Are walk-on rooflights noisy to walk on?
No, not in the way people fear. A properly supported walk-on pane is one of the quieter surfaces to cross…
Are walk-on rooflights slippery when wet?
Clear polished glass is dangerously slippery wet, which is precisely why no walk-on rooflight is supplied with one. The top…
Balustrades, edge protection and where a walk-on panel changes the rules
Most of the difficulty in a walk-on project is not the glass. It is what happens at the edge of…
Can a car be parked on a walk-on rooflight?
Not on a domestic walk-on rooflight, no. Glass that carries vehicles exists, but it is a different product designed to…
Can a Quayside flat have a walk-on rooflight on its terrace?
Often yes, and the reasons it might not are rarely technical. On a Poole quayside flat the deciding factors are…